Last week, Visie director, Warren Swanston had the pleasure of taking Anna from Ozhomenews through a tour of our latest development in Teneriffe. The virtual tour takes you through the penthouse showcasing high ceilings, European appliances and sweeping verandah. To watch the full interview hit the watch now button below. If you would like to […]
READ MORESubmarine-Inspired Building Makes a Splash
Visie’s newest development at 14 Helen Street, Teneriffe was inspired by the suburb’s rich maritime history. Teneriffe was home to the second largest submarine port during World War 2. Obsidian’s curved design draws on the history of this affluent suburb giving it a unique and think-outside-the-box look and feel. To read all about it in […]
READ MOREObsidian Makes a Splash
Recently, Obsidian was featured in the Courier Mail, and what an article it was. With only a few remaining units, now is the time to secure your own home in this beautifully designed building. For more info click here.
READ MOREObsidian Construction Update – March
The team at 5PP are ramping up to completion for our Teneriffe project with PC date in site. Levels 1 and 2 have had final paint coat and silicon completed with defecting to start in the next few days. Level 3 is near completion with final stone installation and tapware to be installed and then […]
READ MOREObsidian Construction Update – January
As we step into the New Year, Obsidian is starting to take shape with the roof finished and cladding detail complete. This month we have seen the side scaffold come down and western wall rendered and painted. Over the next few weeks we will see unveiling of the facade with the back and front scaffolding […]
READ MOREObsidian Construction Update – October 2019
This month was exciting as we saw the precast walls dropped in and propped and level 4 formwork start ready for slab pour next week. Framing almost to completion on levels 1 and 2 with 3 commencing at the end of the month. Plumbing and electrical rough ins have commenced with the majority of rough […]
READ MOREObsidian Construction Update – September 2019
The month of September saw great progress on site with level 3 slab poured, blockwork complete to level 4 and all the formwork complete with reinforcement commencing. It was also exciting news on site with the precast curved walls in place and propped. Level 1 has been framed out, waterproofing to sills and window installation […]
READ MOREObsidian Construction Update – August 2019
August has seen great progress with site a hive of activity in preparation for level 2 slab pour this coming Monday. Slab 1 was poured on the 30th of July and most formwork laid ready for level 2 pour. Basement formwork has been removed and lights completed and installed to storage units. Awesome weather conditions […]
READ MOREObsidian Construction Update – July 2019
Favourable weather during July has seen great progress on site with 5 Point Projects full steam ahead. Basement and storage levels all poured with formwork up to level 1 complete ready to pour next week.
READ MOREObsidian Construction Update – June 2019
Construction Status: The status of works on site Site fully established Crane erected and operating Basement slab complete Blockwalls and column installation underway to underside of ground slab Ground floor slab completed Verticals and blockwork up to level 1 Want more information register your interest on the Obsidian project page by clicking HERE