The month of September saw great progress on site with level 3 slab poured, blockwork complete to level 4 and all the formwork complete with reinforcement commencing. It was also exciting news on site with the precast curved walls in place and propped. Level 1 has been framed out, waterproofing to sills and window installation […]
READ MOREObsidian Construction Update – August 2019
August has seen great progress with site a hive of activity in preparation for level 2 slab pour this coming Monday. Slab 1 was poured on the 30th of July and most formwork laid ready for level 2 pour. Basement formwork has been removed and lights completed and installed to storage units. Awesome weather conditions […]
READ MOREObsidian Construction Update – July 2019
Favourable weather during July has seen great progress on site with 5 Point Projects full steam ahead. Basement and storage levels all poured with formwork up to level 1 complete ready to pour next week.
READ MOREObsidian Construction Update – June 2019
Construction Status: The status of works on site Site fully established Crane erected and operating Basement slab complete Blockwalls and column installation underway to underside of ground slab Ground floor slab completed Verticals and blockwork up to level 1 Want more information register your interest on the Obsidian project page by clicking HERE
READ MOREObsidian Construction Update – May 2019
This month has been exciting with the luffing crane installed, tested and in full operation over the weekend. All steel framing for basement foundation is completed with the basement slab poured. The last of the steel bracing will be removed over the next day and shotcrete to perimeter walls will commence today and blockwork to […]
READ MOREObsidian Construction Update – April 2019
Construction has progressed well this month despite a few wet days and the Easter break. Retention works are almost complete at 95% and excavators have been on site with excavation at 100%. The team at 5 Point Projects are well established on site with amenities and staff sheds in place.
READ MORE