The status of the works on site, as at the date of our site inspection on 13 June 2018, can be briefly described as follows: · Site had been fully established including office and amenities. · Blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORECanopy Taringa – Mid May Update
The status of the works on site, as at the date of our site inspection on 11 May 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORECanopy Taringa – May Update
The status of the works on site, on 26 April 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. The overland flow suspended slab was complete. The […]
READ MORECanopy Taringa – mid April Update
The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORECanopy Taringa – April Update
The status of the works on site, as at the date of our site inspection on 26 March 2018, can be briefly described as follows: Site had been fully established including office and amenities. · Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the […]
READ MORECanopy Taringa – March Update
The status of the works on site, as at the date of our site inspection on 09 March 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORECanopy Taringa – February Update
The status of the works on site, as at the date of our site inspection on 27 February 2018, can be briefly described as follows: Site had been fully established including office and amenities. Bulk excavation works were complete. Detailed excavation was complete. Footings and blockwork retaining walls were complete except to the front of […]
READ MORECanopy Taringa – January Update
Canopy at Taringa is beginning to take shape. The site is fully established with onsite office and amenities. Shake down crossover established with a bulk and detailed excavation works well advanced and onsite stock pile left to back fill. Footings and blockwork retaining walls are well advanced to the back and sides of the site, […]
READ MORECanopy Taringa – December Update
Canopy at Taringa is well underway with the team at Truform having fully established the site with onsite office and amenities. Bulk excavation works of the site have well advanced with onsite stock pile left to back fill. Detailed excavation has well advanced along with footings and blockwork retaining walls to the back and sides […]
READ MOREThe Excavators Have Arrived
The status of the works on site, as at the date of our site inspection on 27th November 2017, can be briefly described as follows: Site had been partly established with safety fencing and portable toilet on site, no offices, amenities established Shake down crossover established. Bulk excavation works have begun on site. The lot […]