The status of works as of the 22nd of August: Scaffolding around the site has come down Roof is nearing completion with installation of soffits and flashing remaining External cladding advanced with one side remaining for installation External painting has begun Framing completed on both levels and rough in services underway and sheeting has commenced […]
READ MOREObsidian – Building Demolition
Demolition of the building on site at Helen Street for Obsidian has commenced over the last week. Earlier during the week saw demolition contractors prepping the site with propping of walls and preparation of trusses. On Saturday demolition started with the removal of both side walls and partial removal of the back wall.
READ MORECanopy – August Update
The status of works as of the 8th of August: Roof trussing and sheeting completed last week Ground level glazing has commenced, as well as rough plumbing and electrical services Level 1 glazing to 90% of the project as well as rough electrical services Exterior cladding and painting to level 1 Installation of insulation
READ MORECanopy Taringa – Mid July Update
The status of the works on site as of the 18th of July 2018: Geocal have fully secured the site with fencing and scaffolding to the entire site setup Geocal contractors on site for framing , roofing and window installation Framing completed 100% for both ground and level one Roof trusses 90% complete Window installation […]
READ MORECanopy Taringa – July Update
The status of the works on site, as at the date of my inspection on 9 July 2018 is: The replacement building Contractor, Geocal Constructions, have taken possession of the site; Blockwork walls are complete; Timber wall framing to ground floor and first floor is 90% complete; Concrete slabs, with the exception of a portion to the […]
READ MOREObsidian Teneriffe – Internal Demolition
Demolition has started on site at Helen Street with the team at Hutchies starting to clear out the internals of the existing building. With the inside almost completely cleared, the building will be set for demolition in the coming weeks.
READ MORECanopy Taringa – June Update
The status of the works on site, as at the date of our site inspection on 13 June 2018, can be briefly described as follows: · Site had been fully established including office and amenities. · Blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORECanopy Taringa – Mid May Update
The status of the works on site, as at the date of our site inspection on 11 May 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORECanopy Taringa – May Update
The status of the works on site, on 26 April 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. The overland flow suspended slab was complete. The […]
READ MORECanopy Taringa – mid April Update
The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MORE