Everton Park on 2 July 2014
The current status of the works on site, as at the date of our inspection 02 July 2014, can briefly described as follows:
* All 33 townhouse structures are complete including cladding, glazing and roofing.
* Scaffold drop underway.
* Plastering complete.
* External rendering almost complete.
* Electrical, plumbing and mechanical fit off is underway.
* Roller door installation underway.
* Tiling well underway,
* Internal painting well underway.
* Joinery installation underway including bench tops and vanities.