The status of the works on site, as at the date of our site inspection on 03 March 2016:
* Basement slab is complete and temporary services including lighting installed.
* Vehicular ramp is poured and complete.
* Block work and columns complete up to under side of Level 2.
* Level 2 Form work at 50%.
* Lift shaft and stairwell walls complete to underside of Level 2.