The month of September saw great progress on site with level 3 slab poured, blockwork complete to level 4 and all the formwork complete with reinforcement commencing. It was also exciting news on site with the precast curved walls in place and propped.
Level 1 has been framed out, waterproofing to sills and window installation commenced with rough in of all services complete. Level 2 will look to have frame, rough in and water proofing complete by mid October. Basement fit off of electrical complete and mechanical ducting well underway.