This month was exciting as we saw the precast walls dropped in and propped and level 4 formwork start ready for slab pour next week. Framing almost to completion on levels 1 and 2 with 3 commencing at the end of the month. Plumbing and electrical rough ins have commenced with the majority of rough in complete to level 1, level 2 to be finished at the end of the week.